NJ Joins NY in Rejecting the Northeast Supply Enhancement Project

New Jersey rejected the plans for Northeast Supply Enhancement pipeline project to move more natural gas to New York City by the winter of 2020-2021, Kallanish Energy reports.

A similar decision was taken last month by New York regulators. The New Jersey Department of Environmental Protection has denied the water-quality certification needed by Williams for the project.

The agency said the project could “adversely impact surface water quality.” Williams is planning to resubmit the application. They have also refiled the permit application to New York regulators and is pending.

The Northeast Supply Enhancement project includes 10 miles of pipeline loops in Pennsylvania, three in New Jersey, 23 miles offshore in New Jersey and New York, a new compressor station in New Jersey and additional horsepower at an existing compressor station in Pennsylvania.

The project is being developed by Transcontinental Gas Pipe Line Co., a Williams’ subsidiary and in New York, the pipeline would stretch under New York Bay to the Queens area of New York City.

National Grid, the largest distributor of natural gas in the northeast U.S said the project is crucial because pipeline capacity to New York is at capacity and natural gas demand in the New York City region is projected to grow by 10% in the next 10 years.

Source:
kallanishenergy

Williams Partners 24-Mile Underwater Pipeline Permit Denied

New York State Department of Environmental Conservation denied a water quality permit for a 24-mile Northeast Supply Enhancement pipeline project from New Jersey to Queens. The pipeline project would expand the Transco pipeline and would allow National Grid to bring natural gas from Pennsylvania’s shale gas fields to the metropolitan region.

The pipeline was initially approved by the Federal Energy Regulatory Commission on May 3, but the environmental groups opposing the pipeline states that the pipeline will threaten marine life and extend the reliance on fossil fuels rather than renewable energy sources. Williams Partners, the pipeline developer said the project is crucial for meeting rising demand for natural gas in New York City and Long Island.

In denying the permit, the New York State Department of Environmental Conservation said the project “fails to meet New York State’s rigorous water quality standards” and “would cause impacts to habitats due to the disturbance of shellfish beds and other benthic resources.”

”Our team will be evaluating the issue and resubmitting the application quickly,” said Chris Stockton, a spokesman for Williams Partners. “We are confident that we can be responsive to this technical concern, meet our customer’s in-service date and avoid a moratorium that would have a devastating impact on the regional economy and environment.”

Source:
pgjonline