FERC Approves $680M Project: 200-Mile Pipeline Moving NatGas from Oklahoma to Gulf Coast Will Connect to Kinder & Boardwalk Pipe

Cheniere Energy and a Washington D.C. private equity firm have received approval from the Federal Energy Regulatory Commission on Wednesday to build the 200-mile Midship Pipeline. The project will move natural gas from Oklahoma to destinations along the Gulf Coast and southeastern United States in Oklahoma.

In a statement issued by the companies, $680 million in financing was secured for the 36-inch diameter natural gas pipeline and a notice was issued for contractors Strike LLC, M.G. Dyess, TRC Pipeline Services and Cenergy LLC to proceed with construction.

The Midship Pipeline is designed to move 1.4 billion cubic feet of natural gas per day from Oklahoma's SCOOP and STACK shale plays to delivery point just north of the Red River near Bennington, Oklahoma. The project is expected to be placed in service by the end of the year.

The pipeline will connect to Kinder Morgan's Midcontinent Express Pipeline and the Boardwalk Pipeline Partners-owned Gulf Crossing Pipeline, allowing natural gas from Oklahoma to move to the TexOk Hub near Atlanta, Texas and the Perryville Hub near Tallulah, Louisiana.

Source:
chron

Cheniere Energy Requests Permission to Bring Billion Dollar Midship NatGas Pipeline in Oklahoma Into Service

Cheniere Energy Inc asked U.S. energy regulators on Friday for permission to start working on their $1.025 billion Midship natural gas pipeline in Oklahoma.

The company asked the FERC for authorization to start building the proposed 234-mile pipeline in three segments. The project is expected to be complete by early 2019, Cheniere said.

Midship is designed to deliver 1.44 billion cubic feet per day (bcfd) of gas from the Anadarko basin to existing pipelines near Bennington, Oklahoma to transport liquefied natural gas to Gulf Coast and Southeast markets.

Expectation of total U.S. LNG export capacity should rise to 8.3 bcfd by the end of 2019 and 9.6 bcfd by the end of 2020 from 3.8 bcfd now.

Most of the U.S. LNG export terminals are located or being built along the Gulf of Mexico in Louisiana and Texas

Source:
Reuters