Phase II Construction of Hillabee Expansion Project Kicks Off

Construction on the second phase of Williams’ Hillabee Expansion project in Chilton County, Alabama has officially started. This includes contractor mobilization, environmental training and site preparation at the location of a nearly seven-mile pipeline loop known as the Rock Springs Loop.

The second phase construction also includes horsepower modifications to two existing Transco compressor facilities. It is anticipated to be placed into service next summer and will increase the Transco pipeline’s capacity by an additional 206,000 dekatherms of natural gas per day.

Another work on nearly four-mile Verbena Loop in Choctaw County, Alabama is scheduled to begin in April.

The first phase of the Hillabee project was successfully placed into service in July 2017. This increased Transco pipeline’s capacity in Alabama by 818,410 dekatherms per day and supplied Florida power generators via the new Sabal Trail pipeline.

Source:
williams