Cactus II Oil Pipeline to Begin Line Fill in a Week

Plains All American Pipeline LP’s Cactus II oil pipeline system will commence line fill within a week, a source with direct knowledge of the matter said. The Cactus II has the capacity of 670,000 barrel per day and runs from Permian Basin to the Corpus Christi, Texas area.

Cactus II project is progressing on schedule for initial service by the end of the third quarter of 2019, the pipeline operator said last month. Commodities merchant Trafigura signed a long-term agreement with Plains last year to transport a total of 300,000 bpd of crude and condensate on the Cactus II pipeline.

“We have over 90% of the pipe in the ground and we’re working diligently toward completion,” a company executive said during its investor day about two weeks ago. Concho Resources Inc., and Anadarko Petroleum Corp are the other two shippers on the Cactus II line.

Source:
pgjonline